Why is the project required?
Sediments wash into canal estates through natural tidal and drainage processes. It requires periodic removal to maintain navigational safety. The process of removal is by dredging.
Council’s Canal Estates Portfolio Asset Management Plan (CEPAMP) defines how we will maintain canals. Maintenance is required to ensure safe navigation and mooring of vessels. Canal depths in the lower reaches of the Pacific Harbour canals have reached the depths nominated in the estate's Long Term Maintenance Plan. Particularly, the lower Skippers Canal and the Marina have reached limits, and maintenance dredging is now required.
The maintenance dredging will ensure safe navigation and mooring within Pacific Harbour.
This is the first large-scale maintenance dredging project we've undertaken at Pacific Harbour. Smaller-scale maintenance dredging, of less than 2,500 cubic metres, was undertaken in 2005/06, 2013 and 2016.
How long will the dredging take?
The planned maintenance dredging is expected to start in mid-2025. It will take approximately eight months to complete.
The set-up of the temporary pipeline from Pacific Harbour to the Ningi DMMF should start in May 2025 and be completed by July 2025. The pipeline and boosters will be in place for the full duration of the dredge works.
Once completed, the next major maintenance dredging project will be in approximately 10 to 20 years.
What is the dredged material?
In 2020, we completed detailed sampling and analysis of sediments from the bottom of Pacific Harbour canals.
Tests found that the material is, for the most part, very soft, dark grey marine clays and sand with occasional clays. It was tested and assessed against relevant guidelines and is suitable for land-based disposal.
How much material will be dredged?
Based on bathymetric surveys of the canals, approximately 80,000 cubic metres of sediment material needs to be removed from the dredging area.
How is the project funded?
The Pacific Harbour Canal Maintenance Special Charge funds the cost of maintenance dredging and spoil disposal. This charge is levied on the canal fronting rateable land within Pacific Harbour.