Planned roadworks

Council roadworks currently underway or planned for the near future. These may result in temporary changes to the traffic conditions, e.g. detours or reduced speed. Observe instructions from work crews and road signage. Plan travel accordingly. The commencement and duration of works are estimates and may be affected by weather conditions or other circumstances.

View weather impacted road closures

For information on other projects and development in your area, visit My Street

Planned roadworks

This element requires javascript to be enabled.

Please wait while we load your map...

Partially closed roads

32 planned partial closures

Suburb Location Estimated start Expected duration Map
BONGAREE Charlotte Avenue - Between Welsby Parade and Winston Drive
Road Resurfacing Work (107359)
24/09/2020 1 Week View Map
BONGAREE Miramar Street - Entire length
Road Resurfacing Work (104218)
25/09/2020 1 Week View Map
BURPENGARY EAST Old Bay Road - Adjacent 486 and 499 Old Bay Road
Culvert Upgrade (105000)
23/06/2020 4 Months View Map
CABOOLTURE Boden Road - Between Alcock Road and 30m South of 55 Boden Road
Road Resurfacing Work (104047)
23/09/2020 1 Week View Map
CABOOLTURE Scarborough Road - Between 55 Scarborough Road and Alcock Road
Road Resurfacing Work (106165)
08/09/2020 3 Weeks View Map
CABOOLTURE Smiths Road - Intersection of Smiths Road and Del Rosso Road
Intersection Upgrade (108014)
13/08/2020 8 weeks View Map
CABOOLTURE Smiths Road - Between Smiths Rd North and Smiths Road South
Road Resurfacing Work (100142)
23/09/2020 1 Week View Map
DAKABIN Plantation Road - Between Old Gympie Road and seal change West of bridge
Road Resurfacing Work (107969)
24/09/2020 1 Week View Map
DONNYBROOK Amy Street - Between Alice Street and end (East)
Road Resurfacing Work (107363)
23/09/2020 1 Week View Map
DONNYBROOK Beerburrum-Donnybrook Road - Between Quinn Road and Bourke Road
Road Resurfacing Work (109213)
24/09/2020 5 Weeks View Map
DONNYBROOK Donnybrook Road - Between Quinn Road and Bourke Road
Road Resurfacing Work (104767)
10/09/2020 1 Week View Map
ELIMBAH Alcock Road - Between Old Gympie Road and Scarborough Road
Road Resurfacing Work (109132)
14/09/2020 3 Weeks View Map
KALLANGUR Freedom Drive - Entire length
Road Resurfacing Work (104749)
14/09/2020 1 Week View Map
MANGO HILL Freshwater Creek Road - Entire length
Road Resurfacing Work (106045)
17/09/2020 1 Week View Map
MARGATE Blackwood Road - Entire length
Road Resurfacing Work (106133)
15/09/2020 1 Week View Map
MOUNT DELANEY Delaney Creek Road - Between Dewhurts Road and access driveway to Paulus Road
Road Resurfacing Work (104568)
21/07/2020 8 Weeks View Map
MOUNT GLORIOUS Harland Road - Entire length
Road Resurfacing Work (108946)
09/09/2020 2 Weeks View Map
MOUNT NEBO Bulcock Avenue - Entire length
Road Resurfacing Work (100778)
24/09/2020 2 Weeks View Map
MURRUMBA DOWNS Bremer Court - Entire length
Road Resurfacing Work (104336)
17/09/2020 1 Week View Map
MURRUMBA DOWNS Paroo Place - Entire length
Road Resurfacing Work (104337)
18/09/2020 1 Week View Map
MURRUMBA DOWNS River Vista Crescent - Entire length
Road Resurfacing Work (104334)
16/09/2020 1 Week View Map
NARANGBA Banyan Street - Between New Settlement Road and Cotton Tree Drive
Road Rehabilitation (101179)
21/09/2020 2 Weeks View Map
NARANGBA Walmsley Street - Entire length
Road Resurfacing Work (106104)
16/09/2020 2 Weeks View Map
NINGI Browns Road - Between Bribie Island Road and 89 Browns Road
Road Resurfacing Work (105624)
09/09/2020 3 Weeks View Map
PETRIE Reid Street - Entire length
Road Resurfacing Work (108757)
23/09/2020 1 Week View Map
PETRIE Rue Montaigne - Between Frenchs Road and Vaucluse Crescent
Road Resurfacing Work (104512)
25/09/2020 1 Week View Map
UPPER CABOOLTURE Frogmouth Court - Entire length
Road Resurfacing Work (104180)
23/09/2020 1 Week View Map
WAMURAN BASIN Basin Road - Between R Sampson Road and Campbells Pocket Road
Road Resurfacing Work (104317)
21/08/2020 3 Weeks View Map
WARNER Lilley Road - Roundabout at Lilley Road, Kremzow Road and Ira Buckby Road West
Pathway Construction (102374)
27/05/2020 5 Months View Map
WOODFORD Archer Street - Between Margaret Street and Kropp Road
Road Rehabilitation (105658)
05/07/2020 4 Months View Map
WOODFORD Peterson Road - Between Archer Street and 70 Peterson Road
Road Resurfacing Work (100812)
21/09/2020 1 Week View Map
WOODY POINT Georgina Street - Between Oxley Avenue and Blakeney Street
Road Resurfacing Work (100247)
16/09/2020 1 Week View Map

Roads with changed conditions

1 planned changes in traffic conditions

Suburb Location Estimated start Expected duration Map
CABOOLTURE Brown Street - Between Ardrossan Road and Elof Road
Road Construction and Upgrade (101267)
23/03/2020 6 Months View Map