Council is restoring sand levels at Woorim Beach ahead of the upcoming 2026-27 summer season.
The work will be carried out between Eighth Avenue and Lowry Street, Woorim and will begin in October 2026.
During the project, about 175,000 cubic metres of offshore sand will be pumped into shallow water. Waves and tides will then move it onto the beach and into the dune system naturally.
Purpose of works
Erosion from weather events in recent years has narrowed the beach, eroded dunes and exposed vegetation roots. This reduces the natural buffer that helps protect nearby public and private property.
The beach nourishment works involve replacing sand lost to help manage coastal erosion. Sand will be placed along approximately 2.7 kilometres of Woorim Beach to restore its width and make it more resilient.
The works will ensure the beach is pristine and accessible for beachgoers during the summer season. This is important for local tourism, businesses and local recreation and amenity.
This project is part of City of Moreton Bay’s broader Coastal Hazard Adaption Strategy to ensure the safety and protection of our community and the environment from natural hazards.
Image caption: Damage caused by erosion at Woorim Beach.
Timing of works
Works are scheduled to begin in early October and are expected to be completed within eight weeks. This is subject to change due to weather conditions and unforeseen circumstances. The aim is to finish in time for the December school holidays.
Beach nourishment activities may operate up to 24 hours a day, seven days a week during the construction period. Other associated work will be done during daytime work hours.
What to expect
Council is working closely with all the relevant stakeholders, including:
- Department of Primary Industries (DPI)
- Other government agencies
- Marine safety authorities
- Environmental regulators
- Surf Life Saving Queensland
- Bribie Island Surf Life Saving Club
- Local environmental groups.
This is to ensure the safety and wellbeing of the community and marine environment throughout the project.
Beachgoers
We aim to minimise disruption to beachgoers while works are carried out. Small sections of Woorim Beach will be temporarily closed during the day throughout the project. Council staff will set up an exclusion zone and monitor the area to ensure safety.
Red and yellow flagged areas will be patrolled by Surf Life Saving Queensland as usual from 8:00 AM to 5:00 PM daily and 7:00 AM to 6:00 PM during school holidays. This is subject to change as conditions change.
In the evenings, affected sections of the beach will be closed to the public and signage will be displayed at access points.
Beachgoers may see the ship delivering sand close to the shoreline several times a day.
Image caption: Beach nourishment work in action during a previous campaign.
Accessibility
Our accessible beach mat will remain in place at Woorim Beach, located at Beach Access Point 12 which adjoins Bluey and Jean Piva Park. Free beach mobility equipment will also continue to be available throughout the project.
Book free beach mobility equipment
Shark Control Program
Shark Control Program drumlines will not be removed during the project. Temporary relocation of some drumlines will be coordinated by the Department of Primary Industries Queensland as the responsible State Government agency.
Project funding
The project has received $4.3 million (excluding GST) through the Coastline Rehabilitation Grant Program. This program is jointly funded by the Australian and Queensland Governments. It supports projects that restore damaged coastlines and improve resilience under the Disaster Recovery Funding Arrangements (DRFA).