William Berry Drive Upgrade completed

An aerial overview shot of the completed William Berry Drive works.

Stage 3B of the William Berry Drive Upgrade is now complete.

This stage included:

  • road pavement reconstruction
  • stormwater drainage upgrades
  • road resurfacing.

These changes improved the safety, condition and long-term performance of William Berry Drive.

The completion of Stage 3B marks the end of the entire William Berry Drive Upgrade. Across all stages, works have delivered significant improvements to the road. 

Across all stages, these works improved:

  • pavement condition
  • drainage infrastructure
  • safety and resilience of the road corridor.

The completion of the project provides long-term benefits for road users. The project supports a safer and more reliable travel for residents, businesses and visitors.

Location

William Berry Drive, Morayfield 4506.  View map

Google Map

Aerial image of William Berry Drive project area separated by three coloured sections. Each colour section corresponds to a closed stage of construction.

The first section (red) represents stage 1 which spanned for 7 weeks. The time period was from mid-May to early July.

The second section (yellow) represents the 4 week period of stage 2. This stage extended from early July through to early August.

The third and final stage indicated by green lasted approximately 6 weeks from early August to mid September. 

Aerial image of William Berry Drive road project area separated by three coloured sections. Each coloured section corresponds to each closed stage of construction.