The Mill at Moreton BayTimeline

Also in this section...

Indicative timeframe of The Mill at Moreton Bay.

Timeline
Phase When What's happening
Phase one 2015 Announcement
August Council secures former Petrie Paper Mill site
October University Precinct officially launches
November Anchor Education Partner announced
Phase two 2016 Initial demolition/remediation and planning
March Demolition of disused buildings commences
May Council commences initial planning consultation
June Council seeks PDA status for the project
August Council releases consultation results which demonstrate strong support
September Queensland Government declares PDA
Phase three 2017 Detailed planning and early works
Year-long Ongoing site remediation work
March Council engages external koala monitoring
April Council commences PDA consultation
August Queensland Government adopted The Mill at Moreton Bay PDA
Development Scheme
Mid-year Council seeking early works approvals for university foundation facilities
November Council finalises the site Koala Management Plan
Late 2017 Council commences early site works
Phase four 2018 Building the future
Early 2018 Construction of the university commences
Year-long Ongoing planning for complementary site uses
Ongoing site works (roads and other infrastructure)
Ongoing site remediation
Ongoing koala and other environmental monitoring
2019 Ongoing site works (roads and other infrastructure) Ongoing site remediation Ongoing koala and other environmental monitoring
Phase five 2020 Delivering on the ground
Early 2020 University opens on site
Ongoing koala and other environmental monitoring
Phase six 2036 Redevelopment of the overall PDA
End 2036 Overall redevelopment expected to be complete