Brays Road and McClintock Drive - Intersection and Road Upgrade

In 2016, the section of Brays Road between Anzac Avenue and Moreton Street, Murrumba Downs was upgraded as part of the Moreton Bay Rail Link project. Council is now extending this upgrade from Moreton Street to Twin Lakes Drive, and along McClintock Drive to Black Duck Creek.

Proposed improvements include:

  • Brays Road to be widened to four traffic lanes, consistent with the 2016 construction works;
  • three new sets of synchronised traffic lights at the intersections with Moreton Street, Normanby Road and McClintock Drive;
  • each new set of traffic lights to include pedestrian crossing facilities;
  • new on-road bicycle lane facilities along Brays Road and McClintock Drive;
  • a new roundabout at the intersection of Brays Road and Twin Lakes Drive; and
  • existing vegetation to be retained as much as possible.

Project timeline

The public feedback period for this project has now closed and council has reviewed the feedback received.

Council is currently in the process of preparing detailed design drawings and undertaking further project preparation, including:

  • locating and recording of significant tree roots using vacuum excavation methods;
  • utility service relocations, expected to be undertaken later this financial year; and
  • compilation of the road construction works package, expected to be tendered during next financial year (2019/20).

Road construction works are currently planned to commence in April 2020.

Project updates

Keep an eye on this page for regular project updates for the Brays Road and McClintock Drive intersections and road upgrade project.

Concept plans showing the proposed changes for discussion with the community:

Further information

For more information about this project contact:

Location of Works - Brays Road and McClintock Drive

PMC Last Updated 17 July 2018

back to top