Woorim Beach sand back-passing trial - quarterly update

Published 13 February 2024

Period covered by this update: 1 July 2023 to 31 Jan 2024

  • 32 active pumping days.
  • Minimum and maximum pumping rates were 38 and 760 cubic metres per day, respectively.
  • Total volume pumped during this period: 12,300 cubic metres.
  • Total volume pumped since 2019: 116,205 cubic metres.
  • The pumping system has been undergoing maintenance from November 2023. No pumping has occurred from November to January inclusive.

The graph shows the daily and cumulative pumping volume of sand from 1 July 2023 to 31 Jan 2024:

Woorim Beach Pumping, graph showing daily and cumulative pumping volume of sand from 1 July 2023 to 31 Jan 2024