Redcliffe Swimming Pool - Filtration systems upgrades project update

Published 11 August 2021

Works Currently Underway:

  • Switchboard installation
  • Plant room configuration
  • Tiling
  • Concourse preparation

Upcoming Works (weather permitting)

  • Wet deck
  • PWD hoist
  • Sewer line installation
  • Balance tank top construction
  • Signage

 