Community use building project update

Published 01 October 2021

Works currently underway:

  • internal painting 95% complete
  • connect mains power to sub board PWD 3
  • sheet set and sand PWD 3 tenancy 3
  • install hand rails to deck
  • exposed aggregate concrete laid
  • carpark demolition complete
  • carpark kerb and channel installed
  • flooring laid 50%
  • PWD 3 tenancy 3 ramp constructed
  • air-con condenser units installed.

Upcoming works (weather permitting):

  • Unity Water stormwater and fire hydrant mains connections complete
  • Unity Water - water meter connections complete levelling and compaction of carpark
  • landscaping of lower level planting area 60% complete
  • landscaping of upper level preparation of additional retaining walls and paving
  • carpark asphalt to be laid
  • access door from storage shed to PWD 3 tenancy 3 to be installed.