Griffin Sports Complex project update

Published 01 November 2021

Works currently underway:

  • roof gutters and flashings
  • floor preparation for surfacing
  • tiling to commence shortly
  • external field fencing
  • dugout structures installation
  • field 2 irrigation
  • field 1 & 3 continue turf establishment
  • topsoil manufacture on site for landscaping.

Upcoming works (weather permitting):

  • import topsoil for field 2
  • turf field 2
  • internal surfacing to all buildings - tiles, epoxy flooring, wall sheeting etc
  • external access maintenance track
  • spread topsoil landscape areas
  • finish remaining concrete pathways.