Griffin Sports Complex project update

Published 03 December 2021

Works currently underway:

  • interior tiling to toilets and change rooms
  • change room wall sheeting and bench seating
  • main building electrical and plumbing rough in prior to wall sheeting
  • spread playing field 2 topsoil and level ready for turf
  • landscaping to north and east of site including gardens and tree planting
  • offset planting
  • installation of back net poles completed.

Upcoming works (weather permitting):

  • landscaping and planting to continue along northern and eastern areas
  • turf field 2 and establish
  • maintenance track to south of playing fields and building
  • continue concrete footpaths
  • internal wall linings and ceilings to main building.