Works currently underway:

  • Road Widening (Northbound lanes): pavement boxing, sub soil drains, subgrade replacement, gravel placement
  • Stormwater Drainage: trenching, pipe laying and pit construction (Northbound lanes)
  • Trunk Water Main: trenching and laying of HDPE trunk water main (Eastern side) across Ashbrook Drive.

Upcoming works (weather permitting):

  • Road Widening (Northbound lanes): gravel placement, bitumen seal
  • Stormwater Drainage: pipe laying and pit construction (Northbound lanes)
  • Trunk Water Main: trenching and laying of HDPE trunk water main (Eastern side) across Ridgegarden Drive
  • Trunk Water Main: trenching and laying of HDPE trunk water main (Eastern side) across Anderson Road
  • Electrical & Communications: relocation works to commence.