Griffin Sports Complex project update

Published 01 October 2021

Works currently underway:

  • installation of roofing flashings
  • installation of internal walls
  • electrical rough in ongoing
  • external concrete around main building
  • facility footpaths
  • bio basin construction ongoing
  • customer property pole installed
  • field 1 topsoil imported and mixing of amendments and additives ongoing
  • field 1 irrigation infrastructure
  • field 2 trim to subgrade level ready for subsoil drainage
  • establish field 3 ongoing
  • installation of rainwater harvesting system ongoing.

Upcoming works (weather permitting):

  • start internal linings to all buildings
  • electrical fit off to all buildings
  • NBN infrastructure install
  • lay turf on field 1 and begin establishment
  • install drainage, import top soil on field 2
  • continue concrete path works
  • construct exterior access track
  • commission pumps for rainwater harvesting system.