Black Duck Lake System rectification project update

Published 08 October 2020

Black Duck Lakes showing unique numbering

HAY: The unique numbering system used for Black Duck Lake refers to its watershed catchment - Hays Inlet. The Black Duck Lake system discharges into Freshwater Creek which in turn discharges into Hays Inlet.

Concept plan

View the concept plan(PDF, 8MB) for the Castle Hill lake (Hay_36). The plan shows the current conditions ‘pre-work’ and the proposed changes for the lake, based community meeting held on 21 August 2020.

Project update

HAY_36

  • Maintenance access - commencing 12 October
  • Weed management - ongoing
  • Formalise stormwater  inlet channels
    • Eastern channel - complete
    • Inlet channel - work commencing 12 October
  • Excavate section of rock pool area and retain dedicated open water channel and improve flushing -complete
  • Infill planting to shallow water margins with wetland plants  - late October
  • Revegetation - starting late October
  • Establishment (irrigate plants) - ongoing
  • Reinstate water level - November

HAY_37

  • Maintenance access - complete
  • Weed management - ongoing
  • Revegetation - complete
  • Establishment (irrigate plants) - ongoing
  • Reinstate water level - Late November

HAY_16

  • Dewater - complete
  • Maintenance access - underway
  • Formalise main inlet and revegetate with macrophytes - underway
  • Formalise stormwater inlet channels - complete
  • Formalise channels within wetland - complete
  • Weed management - ongoing
  • Landscaping/ revegetation - commencing 19 October
  • Establishment (irrigate plants) - ongoing

HAY_35

  • Maintenance access - complete
  • Formalise stormwater  inlet channels - underway
  • Weed management - ongoing
  • Revegetation of wetland area - complete
  • Establishment (irrigate plants) - ongoing
  • Reinstate water level - Late October

HAY_38

  • Maintenance access  - work to start November

All on-ground work will be completed as per schedule weather permitting.